Audit of Claxton

Type of audit

External Audits
Claxton

Auditee/Customer

Claxton
DNO/WE

Date

2024/07/04

521 days ago

Findings

17
Number of findings

Status

In process
External Audits


Audit of Claxton
Summary

A Verification of Claxton Engineering Services AS (Claxton) was conducted 4th of July 2024 according to DNO Norge AS’ (DNO’s) Audit, Review and Verification (ARV) Plan for the Falstaff exploration well and Well Expertise’ (WE’s) ARV plan for 2024. The objective was to verify that Claxton operates in compliance with contractual requirements, Norwegian regulations and relevant standards, and to get a better understanding of the offered equipment for DNO’s exploration drilling at Falstaff.

The Verification was carried out by verifying received documentation and presentation of requested topics.

The Verification was well prepared and facilitated in a good atmosphere by Claxton, and everyone participating were very open and honest.

The Verification team identified no (0) non-conformances, one (1) observation, eight (8) improvement suggestions, and seven (8) actions. The findings are listed in Chapter 5. None of the findings are critical for the upcoming Falstaff operation.

Findings

  • Observation

    Closed


    Closed


    Deadline was:

    OBS-1: Seems to miss cross reference the actions in the risk register to the Action register.
    During the verification Claxton could not present a systematic and methodical approach to how mitigating actions from risk assessments are closed. And reviewing documentation received, the verification team does not see that it is clearly stated how to secure that mitigations are implemented and documented.

    The Verification team suggest that Claxton update relevant procedures to reflect this and looks into implementing a good way of documenting closure (how and where).

    06.09.24: A project risk register review was conducted on 09 August. In attendance was Business Development, Operations Manager, Project Lead and QHSE. The project is running via the rolling action register which captures the relevant mitigation actions. Confirmation is required from the Project Lead that this process is fully aligned to close – since in process, case closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-1: How Claxton secures that they are updated according to regulations does not seem robust. Very dependent on externals.
    Regulatory compliance is secured in the Compliance obligations register (COR). The COR is developed by Antenor OTG, but no review cycle is implemented securing regular updates. Claxton monitor through the Barber index and also have Medco OHS a support for health-related regulatory updates. By the time of the verification Claxton’s legal compliance was 81 %, due to i.a. one NCR related to GDPR (work ongoing).

    Claxton should get in place better routines to ensure that new or updated regulatory requirements are caught (Lovdata.no, information letters from Havtil, regular reviews, etc.) and also to secure ownership of the COR.

    29.08.24: Status requested.
    06.09.24: Procurement are liaising with Lovdata for a subscription, however the VP QHSSE for Claxton, Nathan Darnell is also exploring utilising Barbour Indexes for all sites which includes local legislation. The PO for Lovdata subscription is on hold until the decision has been made on utilising Barbour. Barbour EHS (barbour-ehs.com)
    28.10.24: Lovdata subscription has been authorised. We’ve received the log ins and just need to register – case closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-2: Several open MoCs and NCRs in Intelex.
    When receiving documentation before the Verification, the status was 26 open Non-Conformance Reports (NCR) and 19 open MoC for May. The amount has been increasing over the last months, and at the Verification the number had increased further for June.

    Claxton should start defining and prioritising the critical ones, and secure that the «quick fixes» (closed, approved, and rejected ones) are marked as closed.

    29.08.24: Status requested.
    06.09.24: A monthly Intelex meeting has been initiated to address and prioritise open actions. This will be ongoing throughout the next 12 months. Closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-3: Would be beneficial to have a Norwegian HSE resource.
    The position as Regional QHSE Manager is rather new in Claxton and covers both UK and Norway and thereby have a wide range of work tasks. Having a dedicated HSE resource in Norway, would strengthen the company and securing even better management of the QHSE area (ref. also IMP-2).

    Claxton is requested to give feedback if this is a resource they will take onboard.

    29.08.24: Status requested.
    06.09.24: The position of QHSE Advisor has been approved within the Norwegian organisation. Currently progress is interviewing three candidates in the next two weeks or so. Failing this, there is also an appetite to recruit a temporary resource.
    21.10.24: We consider this as closed as they are in a process.

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-4: Risk Matrix Acteon: The company «accepts» one fatality/death every third year.
    The risking of fatalities should be updated in all risk matrices, as Claxton (Acteon) now “accepts” fatalities when they are less frequent. One fatality (death) every 3rd year is considered as a medium and acceptable risk.

    The Verification team’s experience is also that the risk differs between countries and projects, especially when it comes to cost. It may also be beneficial to make a Bridging document for securing proper values and proper risking for projects in Norway.

    29.08.24: Status requested.
    06.09.24: There have been discussions on amending the RCM, but there are at a higher level as the RCM is an Acteon Group tool. This resides with VP QHSSE for Claxton, Nathan Darnell.
    21.10.24: Asked for the feedback from Mr. Darell
    28.10.24: Nathan is on leave. He’s considering on removing the time period in the risk classification matrix. Closed, as we believe that this matter is followed up

  • Improvement

    In Process

    In Process


    Deadline was:

    IMP-5: Maintenance system: Today’s tagging system is resource demanding. Risk for loosing parts or tags.
    Claxton do not have a proper maintenance system. Every part and equipment are tagged. The workshop appears very clear and orderly, but the chance of errors occurring is present. Parts of the labels can wear off during moving, transport or storage, so that equipment that actually has a red label becomes an orange, dark green or green category. It is also a risk that equipment/parts can be lost.

    As of today, there have not been any incidents where this has occurred, but the verification team considers this a significant risk. In addition, the system is very labour-intensive. Systematising and digitising the equipment will free up capacity and increase efficiency, as well as reduce risk.

    29.08.24: Status requested.
    06.09.24: No update to communicate.
    21.10.24: Wanted feedback – Would have been nice to receive a plan for this or if there has been any discussions, or fora where this has been discussed.
    28.10.24: PMM (Product Maintenance Manual) and tagging system are in place and in the testing phase. An APP for maintenance registration digitally is begin worked on and tentatively a beta version will be released at the end of the year. I will contact the Global resource whose leading the initiative for a plan.
    21.03.25: Asked for status and plan

  • Improvement

    In Process

    In Process


    Deadline was:

    IMP-6:Try to capture CO2 footprint per project, as DNO (and other operator) report on Scope 3 emissions.
    For the Falstaff operation DNO wants to get an overview of Scope 3 emissions. It would be nice if Claxton tries to capture CO2 footprint for this project. We assume that this will be required from several operators going forward.

    The Verification team see that Claxton has started the process of mapping CO2 equivalents from several emission points (flights, transportation, electricity etc.), and experience from this can be built on for future projects.

    29.08.24: Status requested.
    06.09.24: This is sitting with VP QHSSE for Claxton, Nathan Darnell. As you are aware from the audit our SPI data is collated monthly across the sites as a whole and to address this per project across five operating sites is a significant undertaken.
    21.10.24: Yes, this is a huge task and we know this will take time and resources. But if we just could get a confirmation that this is something Claxton will work on going forward, and a plan for this can maybe be brought forward?– we will close the case from our side.
    28.10.24: Nathan Darnell has a proposal from an environmental consultant to provide support in the new year on ESG, including more detailed emissions reporting.
    21.03.25: Asked for a Falstaff report/numbers

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-7: We recommend that Claxton starts preparing for making the Transparency Statement for 2024.
    Claxton will be subject to the Transparency Act for 2024 as they tick off at least two of the below requirements:
    • Sales revenues above MNOK 70
    • Balance sheet total of more than MNOK 35
    • Average number of employees in the financial year more than 50
    Claxton’s Human rights and Global labour principle policy does not reflect all aspects of the Transparency Act.

    The Verification team recommends Claxton to develop a system for reporting according to the Act, to be prepared for the Transparency Statement in 2025. There are several statements available on Norwegian companies websites at it is required to have the statement open for public.

    29.08.24: Status requested.
    06.09.24: Roger Sandanger has raised this with Laura Claxton COO, it has been agreed that a gap analysis is required to be undertaken. This was communicated on 03 September.
    21.10.24: Requested status: Any news? As long as this is on Claxton’s agenda, we will close the case.
    28.03.24: Status currently is that work is ongoing from Supply Chain to prepare for a report for 2024. Just recently there has been interaction to take synergies from other Acteon Companies established in Norway. Case considered closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-8: Secure that the requirements in the Transparency Act are implemented in the Vendor Questionnaire.
    Claxton has a very good and thorough system for checking and approving suppliers by use of a vendor questionnaire. The Transparency Act requires that the business must assess the risk of violations of or negative consequences of breach of human rights in its supply chain, all the way back to the raw material stage. As per todays, Claxton’s questionnaire does not include relevant requirements related to the Act.

    Update the Questionnaire

    29.08.24: Status requested.
    06.09.24: The Group Supply Chain Manager has been tasked with undertaking a gap analysis on the requirements to be included in the vendor questionnaires.
    21.10.24: Feedback: We then consider this case closed.

  • Actions

    Closed


    Closed


    A-1: Claxton to send presentation

    Received 04.05.24.

  • Actions

    Closed


    Closed


    A-2: DNO to send presentation

    Sent 05.08.24

  • Actions

    Closed


    Closed


    Deadline was:

    A-3: The status of Falstaff Risk Register was uncertain.

    Claxton to send Falstaff Risk register or status on the work, and overview of major risks.

    29.08.24: Status requested.
    21.10.24: Status requested again…
    28.10.24: Received Rolling Action Register – action closed

  • Actions

    Closed


    Closed


    A-4: Claxton to send Supplier approval and management procedure

    Received 04.07.24

  • Actions

    Closed


    Closed


    A-5: Claxton to share “Digital ideas map” if possible

    Received 04.07.24

  • Actions

    Closed


    Closed


    A-6: Post verification action: Claxton to provide needed SDS’ for chemicals planned used offshore. To be sent to environmental@wellexpertise.com.

    Send before operation start

    29.08.24: Status requested.
    21.10.24: We have not received any SDS’ for the Falstaff operation. Could you please help us provide these ASAP?
    28.10.24: Received SDS’ for Rocol and Molykote – action closed

  • Actions

    Closed


    Closed


    Deadline was:

    A-7: Claxton to Invite DNO and WE to open day in September (Lazer cutting to be presented)

    29.08.24: Status requested.
    04.09.24: Invitation received

  • Actions

    Closed


    Closed


    A-8: Changes of key personnel or suppliers must be reported to WE (Phil Hardy)

    Continous in operation
    No changes during operation



Additional Documentation

WE-EA-2024-03-Verification-Report-Claxton-Engineering-final.pdf


WE-EA-2024-03-Verification-Report-Claxton-Engineering-final.pdf




New Audit Report

You do not have permission to view this form.


\n


Claxton

No person selected

Report No.

6515
Audit of Claxton

Type of audit

External Audits
Claxton

Auditee/Customer

Claxton
DNO/WE

Date

2024/07/04

521 days ago

Findings

17
Number of findings

Status

In process
External Audits


Audit of Claxton
Summary

A Verification of Claxton Engineering Services AS (Claxton) was conducted 4th of July 2024 according to DNO Norge AS’ (DNO’s) Audit, Review and Verification (ARV) Plan for the Falstaff exploration well and Well Expertise’ (WE’s) ARV plan for 2024. The objective was to verify that Claxton operates in compliance with contractual requirements, Norwegian regulations and relevant standards, and to get a better understanding of the offered equipment for DNO’s exploration drilling at Falstaff.

The Verification was carried out by verifying received documentation and presentation of requested topics.

The Verification was well prepared and facilitated in a good atmosphere by Claxton, and everyone participating were very open and honest.

The Verification team identified no (0) non-conformances, one (1) observation, eight (8) improvement suggestions, and seven (8) actions. The findings are listed in Chapter 5. None of the findings are critical for the upcoming Falstaff operation.

Findings

  • Observation

    Closed


    Closed


    Deadline was:

    OBS-1: Seems to miss cross reference the actions in the risk register to the Action register.
    During the verification Claxton could not present a systematic and methodical approach to how mitigating actions from risk assessments are closed. And reviewing documentation received, the verification team does not see that it is clearly stated how to secure that mitigations are implemented and documented.

    The Verification team suggest that Claxton update relevant procedures to reflect this and looks into implementing a good way of documenting closure (how and where).

    06.09.24: A project risk register review was conducted on 09 August. In attendance was Business Development, Operations Manager, Project Lead and QHSE. The project is running via the rolling action register which captures the relevant mitigation actions. Confirmation is required from the Project Lead that this process is fully aligned to close – since in process, case closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-1: How Claxton secures that they are updated according to regulations does not seem robust. Very dependent on externals.
    Regulatory compliance is secured in the Compliance obligations register (COR). The COR is developed by Antenor OTG, but no review cycle is implemented securing regular updates. Claxton monitor through the Barber index and also have Medco OHS a support for health-related regulatory updates. By the time of the verification Claxton’s legal compliance was 81 %, due to i.a. one NCR related to GDPR (work ongoing).

    Claxton should get in place better routines to ensure that new or updated regulatory requirements are caught (Lovdata.no, information letters from Havtil, regular reviews, etc.) and also to secure ownership of the COR.

    29.08.24: Status requested.
    06.09.24: Procurement are liaising with Lovdata for a subscription, however the VP QHSSE for Claxton, Nathan Darnell is also exploring utilising Barbour Indexes for all sites which includes local legislation. The PO for Lovdata subscription is on hold until the decision has been made on utilising Barbour. Barbour EHS (barbour-ehs.com)
    28.10.24: Lovdata subscription has been authorised. We’ve received the log ins and just need to register – case closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-2: Several open MoCs and NCRs in Intelex.
    When receiving documentation before the Verification, the status was 26 open Non-Conformance Reports (NCR) and 19 open MoC for May. The amount has been increasing over the last months, and at the Verification the number had increased further for June.

    Claxton should start defining and prioritising the critical ones, and secure that the «quick fixes» (closed, approved, and rejected ones) are marked as closed.

    29.08.24: Status requested.
    06.09.24: A monthly Intelex meeting has been initiated to address and prioritise open actions. This will be ongoing throughout the next 12 months. Closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-3: Would be beneficial to have a Norwegian HSE resource.
    The position as Regional QHSE Manager is rather new in Claxton and covers both UK and Norway and thereby have a wide range of work tasks. Having a dedicated HSE resource in Norway, would strengthen the company and securing even better management of the QHSE area (ref. also IMP-2).

    Claxton is requested to give feedback if this is a resource they will take onboard.

    29.08.24: Status requested.
    06.09.24: The position of QHSE Advisor has been approved within the Norwegian organisation. Currently progress is interviewing three candidates in the next two weeks or so. Failing this, there is also an appetite to recruit a temporary resource.
    21.10.24: We consider this as closed as they are in a process.

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-4: Risk Matrix Acteon: The company «accepts» one fatality/death every third year.
    The risking of fatalities should be updated in all risk matrices, as Claxton (Acteon) now “accepts” fatalities when they are less frequent. One fatality (death) every 3rd year is considered as a medium and acceptable risk.

    The Verification team’s experience is also that the risk differs between countries and projects, especially when it comes to cost. It may also be beneficial to make a Bridging document for securing proper values and proper risking for projects in Norway.

    29.08.24: Status requested.
    06.09.24: There have been discussions on amending the RCM, but there are at a higher level as the RCM is an Acteon Group tool. This resides with VP QHSSE for Claxton, Nathan Darnell.
    21.10.24: Asked for the feedback from Mr. Darell
    28.10.24: Nathan is on leave. He’s considering on removing the time period in the risk classification matrix. Closed, as we believe that this matter is followed up

  • Improvement

    In Process

    In Process


    Deadline was:

    IMP-5: Maintenance system: Today’s tagging system is resource demanding. Risk for loosing parts or tags.
    Claxton do not have a proper maintenance system. Every part and equipment are tagged. The workshop appears very clear and orderly, but the chance of errors occurring is present. Parts of the labels can wear off during moving, transport or storage, so that equipment that actually has a red label becomes an orange, dark green or green category. It is also a risk that equipment/parts can be lost.

    As of today, there have not been any incidents where this has occurred, but the verification team considers this a significant risk. In addition, the system is very labour-intensive. Systematising and digitising the equipment will free up capacity and increase efficiency, as well as reduce risk.

    29.08.24: Status requested.
    06.09.24: No update to communicate.
    21.10.24: Wanted feedback – Would have been nice to receive a plan for this or if there has been any discussions, or fora where this has been discussed.
    28.10.24: PMM (Product Maintenance Manual) and tagging system are in place and in the testing phase. An APP for maintenance registration digitally is begin worked on and tentatively a beta version will be released at the end of the year. I will contact the Global resource whose leading the initiative for a plan.
    21.03.25: Asked for status and plan

  • Improvement

    In Process

    In Process


    Deadline was:

    IMP-6:Try to capture CO2 footprint per project, as DNO (and other operator) report on Scope 3 emissions.
    For the Falstaff operation DNO wants to get an overview of Scope 3 emissions. It would be nice if Claxton tries to capture CO2 footprint for this project. We assume that this will be required from several operators going forward.

    The Verification team see that Claxton has started the process of mapping CO2 equivalents from several emission points (flights, transportation, electricity etc.), and experience from this can be built on for future projects.

    29.08.24: Status requested.
    06.09.24: This is sitting with VP QHSSE for Claxton, Nathan Darnell. As you are aware from the audit our SPI data is collated monthly across the sites as a whole and to address this per project across five operating sites is a significant undertaken.
    21.10.24: Yes, this is a huge task and we know this will take time and resources. But if we just could get a confirmation that this is something Claxton will work on going forward, and a plan for this can maybe be brought forward?– we will close the case from our side.
    28.10.24: Nathan Darnell has a proposal from an environmental consultant to provide support in the new year on ESG, including more detailed emissions reporting.
    21.03.25: Asked for a Falstaff report/numbers

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-7: We recommend that Claxton starts preparing for making the Transparency Statement for 2024.
    Claxton will be subject to the Transparency Act for 2024 as they tick off at least two of the below requirements:
    • Sales revenues above MNOK 70
    • Balance sheet total of more than MNOK 35
    • Average number of employees in the financial year more than 50
    Claxton’s Human rights and Global labour principle policy does not reflect all aspects of the Transparency Act.

    The Verification team recommends Claxton to develop a system for reporting according to the Act, to be prepared for the Transparency Statement in 2025. There are several statements available on Norwegian companies websites at it is required to have the statement open for public.

    29.08.24: Status requested.
    06.09.24: Roger Sandanger has raised this with Laura Claxton COO, it has been agreed that a gap analysis is required to be undertaken. This was communicated on 03 September.
    21.10.24: Requested status: Any news? As long as this is on Claxton’s agenda, we will close the case.
    28.03.24: Status currently is that work is ongoing from Supply Chain to prepare for a report for 2024. Just recently there has been interaction to take synergies from other Acteon Companies established in Norway. Case considered closed

  • Improvement

    Closed


    Closed


    Deadline was:

    IMP-8: Secure that the requirements in the Transparency Act are implemented in the Vendor Questionnaire.
    Claxton has a very good and thorough system for checking and approving suppliers by use of a vendor questionnaire. The Transparency Act requires that the business must assess the risk of violations of or negative consequences of breach of human rights in its supply chain, all the way back to the raw material stage. As per todays, Claxton’s questionnaire does not include relevant requirements related to the Act.

    Update the Questionnaire

    29.08.24: Status requested.
    06.09.24: The Group Supply Chain Manager has been tasked with undertaking a gap analysis on the requirements to be included in the vendor questionnaires.
    21.10.24: Feedback: We then consider this case closed.

  • Actions

    Closed


    Closed


    A-1: Claxton to send presentation

    Received 04.05.24.

  • Actions

    Closed


    Closed


    A-2: DNO to send presentation

    Sent 05.08.24

  • Actions

    Closed


    Closed


    Deadline was:

    A-3: The status of Falstaff Risk Register was uncertain.

    Claxton to send Falstaff Risk register or status on the work, and overview of major risks.

    29.08.24: Status requested.
    21.10.24: Status requested again…
    28.10.24: Received Rolling Action Register – action closed

  • Actions

    Closed


    Closed


    A-4: Claxton to send Supplier approval and management procedure

    Received 04.07.24

  • Actions

    Closed


    Closed


    A-5: Claxton to share “Digital ideas map” if possible

    Received 04.07.24

  • Actions

    Closed


    Closed


    A-6: Post verification action: Claxton to provide needed SDS’ for chemicals planned used offshore. To be sent to environmental@wellexpertise.com.

    Send before operation start

    29.08.24: Status requested.
    21.10.24: We have not received any SDS’ for the Falstaff operation. Could you please help us provide these ASAP?
    28.10.24: Received SDS’ for Rocol and Molykote – action closed

  • Actions

    Closed


    Closed


    Deadline was:

    A-7: Claxton to Invite DNO and WE to open day in September (Lazer cutting to be presented)

    29.08.24: Status requested.
    04.09.24: Invitation received

  • Actions

    Closed


    Closed


    A-8: Changes of key personnel or suppliers must be reported to WE (Phil Hardy)

    Continous in operation
    No changes during operation



Additional Documentation

WE-EA-2024-03-Verification-Report-Claxton-Engineering-final.pdf


WE-EA-2024-03-Verification-Report-Claxton-Engineering-final.pdf



\n”}}]}]}]},{“type”:”section”,”props”:{“class”:”uk-hidden”,”id”:”newreport”,”image_position”:”center-center”,”padding”:”none”,”style”:”default”,”title_breakpoint”:”xl”,”title_position”:”top-left”,”title_rotation”:”left”,”vertical_align”:””,”width”:”default”},”children”:[{“type”:”row”,”children”:[{“type”:”column”,”props”:{“image_position”:”center-center”,”position_sticky_breakpoint”:”m”},”children”:[{“type”:”html”,”props”:{“content”:”

\n

\n

New Audit Report